World's tallest bridge progresses with steel truss milestone

By YANG JUN and LIU BOQIAN in Guiyang | chinadaily.com.cn | Updated: 2024-11-07 16:45
Share
Share - WeChat
The 215-ton truss lifted on Monday will be the primary support for the Huajiang Grand Canyon Bridge's concrete deck. [Photo by Liu Boqian/For chinadaily.com.cn]

Huajiang Grand Canyon Bridge in Guizhou province completed its first steel truss lift on Monday, marking a major step toward next year's scheduled opening.

Towering 625 meters above the Beipan River, the 2,890-meter-long bridge is part of a regional expressway project. Construction began in 2022. Upon completion in 2025, it will set a new record as the world's tallest bridge.

The 215-ton truss lifted on Monday will be the primary support for the concrete deck. It is one of 93 truss segments, weighing more than 21,000 tons, that will form the bridge's main structure.

Considering such a high weight, engineers deployed the world's largest cable crane system, incorporating transport, lifting and smart monitoring systems to navigate the challenging terrain of steep mountains and deep valleys.

More than 30 high-definition cameras and numerous sensors provide real-time data to ensure safe, precise positioning.

"The smart lifting system, developed in-house, uses the Beidou navigation and IoT technologies for precise positioning. The system improves both the accuracy and safety of the lift while reducing labor costs," explained Wang Songyu, the construction project manager.

Inside the bridge's smart control center, only a few operators manage the installation process, with the system reducing a task that once required 20 people to one that now requires only two operators.

Guizhou's rugged terrain has driven the need for extensive bridge infrastructure to support its traffic network. Once completed, the Huajiang Grand Canyon Bridge will reduce travel time between its two ends from an hour to just one minute, significantly improving local mobility and boosting tourism to nearby attractions such as the famous Huangguoshu Waterfall.

The project team said the construction is now 75 percent completed, with all the main cables in place. The remaining steel truss sections are expected to be installed around the Chinese Lunar New Year, and the bridge is on track to open in the latter half of 2025.

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 成人一级 | 短视频网站免费观看 | 免费一级毛片在线播放欧美 | 免费黄色福利 | 一区二区福利视频 | 奇米色偷偷 | 欧美成人欧美激情欧美风情 | 一区二区成人 | 欧美激情在线观看一区二区三区 | 久久成人高清 | 精品国精品国产自在久国产应用 | 亚洲国产精品一区二区第一页 | 欧美极品jizzhd欧美 | 国产精品久久久久无码av | 免费一区 | 青青久久久国产线免观 | 日韩在线视频观看 | 欧美午夜一艳片欧美精品 | 另类国产ts人妖高潮系列视频 | 免黄网站 | 欧美黑人性受xxxx喷水 | 一区二区三区在线 | 日本 | 精品久久久久区二区8888 | 国产小视频在线高清播放 | 久久久久黄 | 久久精品国产亚洲 | 91短视频网址 | 国产成人久久婷婷精品流白浆 | 视频在线观看一区 | 超级成人97碰碰碰免费 | 青娱乐激情视频 | 成年网站在线观看 | 欧美a级成人淫片免费看 | 91国在线啪 | 欧美啪啪网址 | 在线播放日本爽快片 | 欧美人成在线视频 | 日本不卡一区 | 播五月开心婷婷综合 | 亚洲精品网站日本xxxxxxx | 黄色免费av|