Three Gorges project running well

(Xinhua)
Updated: 2007-06-30 22:03

Chinese auditors said it found no embezzlement or misappropriation of construction fund in the ongoing Three Gorges project, however, they also detected some problems and flaws in the project management.

The National Audit Office (NAO) said the overall quality control of the project was fine and total investment were kept under control.

All 11 major projects were up to the standards, as were main materials such as steel and cement, said an audit report by the NAO.

It said total inflation-adjusted investment, expected to be 78 billion yuan, could be more than 35 billion yuan less than planned in 1994. By the end of 2005, the country had spent 64.2 billion yuan on the project.

The NAO, however, also detected extra construction costs of 488 million yuan, most of which was incurred by project construction contractors who exaggerated their expenditure.

The office also found 20.4 hectares of land illegally used without governmental permission, while another 110 hectares approved for use had been left idle.

"The problems are largely due to lack of laws and regulations and imperfection in internal control," said Pan Xiaojun, senior official with the NAO.

The company said it had already corrected the use of 139 million yuan of fund involving violation of rules, and a total 17 measures had been adopted to improve management over the project.

The office said 21 power station construction projects, most of which involved a single contract value of less than 10 million yuan were not put out to tender.

A few construction companies were discovered to have subcontracted their projects against regulations and obtained illegal charge of 53.45 million yuan.

About half of the 1,448 supervisors sampled were found to have no licenses for the work.

The China Three Gorges Corporation said it had strengthened the implementation of public bidding to ensure the fairness of the results and avoid the influence of people, and it also added detailed terms about contracting in contracts to prevent illegal contracting.

The unlicensed supervisors had been fired and supervision over the project supervisors were enhanced, according to the company.

The report said that the project across the Yangtze River, the construction of which began in 1993, had played a "better-than-expected" role in flood prevention, power generation and shipping.

"It's possible to put the project into full operation by 2009 as planned, and the project is running a bit ahead of schedule," it said.

The fourteen generators in a power plant had been put into operation a year earlier than planned in 2005, the office said.

Upon its completion, the Three Gorges dam will produce 85 billion kwh of electricity annually for supply to central and eastern China.

The dam, which is 2,309 meters long and 185 meters high, will be installed with 26 turbo-generators, each with a generation capacity of 700,000 kilowatts.

The audit, which took 150 auditors more than six months to complete, covered areas including fund raising, management and use, construction management as well as benefit of the project.



Top China News  
Today's Top News  
Most Commented/Read Stories in 48 Hours
主站蜘蛛池模板: 妈妈的朋友酷客影响 | 亚洲av一级毛片特黄大片 | 一级黄色毛片视频 | 久在线 | 亚洲一区二区三区深夜天堂 | 久久99精品视香蕉蕉 | 九九视频只有精品六 | 欧美一区二区三区视频 | 色噜噜色噜噜天天拍一拍 | 精品国产一区二区三区成人影院 | 在线观看亚洲 | 国产精品资源在线观看网站 | 一级黄色毛片 | 日韩a级片 | 理论片91 | 成人黄色免费 | 久草视频在线资源站 | 色五月婷婷成人网 | 日韩欧美一区二区三区在线 | 一区二区av| 日韩高清一区 | 欧美另类视频在线 | 亚洲A片V一区二区三区有声 | 欧美成人私人视频88在线观看 | 天天操 夜夜操 | 亚洲国产七七久久桃花 | 亚洲综合色网站 | 国产精品久久久久久久久久红粉 | 日韩免费在线观看视频 | 草草影院永久地址 | 精品欧美亚洲韩国日本久久 | 亚洲国产精品无码AV久久久 | 91国内精品久久久久怡红院 | 男女交叉视频 | 日韩福利在线 | 亚洲欧美日韩高清 | 成年人在线播放视频 | 电家庭影院午夜 | 国产精品揄拍100视频最近 | 婷婷综合网站 | 久草在线观看首页 |