Adigrat-Adwa-Shire Road upgrading project in Ethiopia starts officially

Updated: 2008-03-01

The subjected project contracted by CGGC was officially commenced from km+275.00-km+282.5 on Feb 22, 2008 in witness of representatives from the Employer, the Employer's Engineer and the Contractor.

Located in Shire-Adiabu, north-west of Ethiopia the Project is of 91.8 kilometers long and to be completed within 1095 days contractually.

Efficient measures were taken by CGGC to overcome water shortage and poor resources such that the start point (km+275.00~km+282.5) is ready for commencement.

 